Longitudinal post-tensioning
Rijssen, 2009-2010
Project: 2 Traffic decks, 2 Railway decks
Contractor: Reef Infra bv
's-Hertogenbosch, 2009
Project: Wild-life crossing (23ton) and subway (63 ton)
Contractor: Colijn Aannemersbedrijf BV
Walcheren, 2009
Project: Aqueduct N57 - longitudinal post-tensioning of a submersible element
Contractor: Rijskwaterstaat/Strukton Civiel
Venlo, 2007
Project: 2 ecodivers RW73 Venlo, 8 m/ton
Contractor: Martens Prefab Beton
Barendrecht, 2007
Project: Bridge over the Agaatlaan, 3 m/ton
Contractor: Colijn Aann.bedrijf BV
Son, 2007
Project: Keggeviaduct Haarlem, 2 m/ton
Contractor: Betonson B.V.
Venlo, End of November 2006
Project: Strengthening of a cellar’s roof, 98,5 m/ton
Contractor: Bouwbedrijf Goldewijk B.V. / Caseco
Venlo, End of September 2006
Project: Road Section B - 3 decks
Contractor: Betonson-Besix
Rotterdam, March 2006
Project: 9 Bridges Lage Limiet
Contractor: WACO B.V.
Zoetermeer, summer 2006
Project: Widening four flyovers of Australiëweg:
KW 43 and 44, KW 45 and 46
Contractor: Colijn Aannemersbedrijf B.V.
Alkmaar, January 2006
Project: N 242, supply of 100 metric tons
Contractor: Beton- en Waterbouw Heijmans
Swalmen, 2005
Project: Highway A73 in 2 decks, 16,8 m/ton
Contractor: Combination Strukton/Besix - Colijn Aannemersbedrijf B.V.
Albrandswaard, 2004
Project: 1 deck over the Agaatlaan
Contractor: Colijn Aannemersbedrijf BV
Nootdorp, 2004
Project: Pedestrian bridge Balij
Contractor: GEKA - Dordrecht
Albrandswaard, 2004
Project: Bridge Onyx Parelmoer
Contractor: Colijn Aannemersbedrijf BV
Rotterdam, 2003
Project: Kortsluitroute Engineering Structure A - Groene Kruisweg
Specification: 37 strand system, 445 m/ton
Contractor: Strukton Betonbouw B.V.
Rotterdam, 2003
Project: Bridge in the Kanaalweg, 80,9 m/ton
Contractor: Van der Horst B.V., HSL
Son, 2003
Project: Bridge prefabricated Pier Construction
Specification: Longitudinal post-tensioning in prefabricated pretensioned beams
Contractor: Beton Son B.V.
Eindhoven, 2003
Project: Beukenlaan, 5,4 m/ton
Contractor: Combination Rasenberg/Strukton
Roermond, 2003
Project: Underpass Scheperweg in deck under the railway
Contractor: ProRail in combination with Colijn Aannemersbedrijf B.V.
Amsterdam, 2003
Project: Zinc Subway NoordZuidlijn onder Amsterdam CS and the IJ, 83,7 m/ton
Contractor: Combination Strukton/Heijmans
Woerden-Harmelen, 2002
Post tensioning in concrete surface south and north Leidsestraatweg/ Oude Rijn/ Breeveld in the railwaytrack Woerden-Harmelen- phase 1
Contractor – ProRail BV
Roermond
Project: Zinc Subway under the A73, 135 m/ton
Contractor: Combination Besix/Strukton |